Enhancing flood protection for the Mill Creek area of Kelowna, British Columbia

CIMA+ (through MidSea Engineering) led the upgrade of the Mill Creek diversion structure for the City of Kelowna to address increasing flood risks driven by climate change. The project enhanced hydraulic capacity, improved public safety and fish passage, and delivered resilient, sustainable infrastructure that will protect communities and support environmental stewardship for years to come.

Kelowna experienced several floods in the Mill Creek area during the 2010s due to high water levels in the spring. Although a structure had been built on Mill Creek in 1989 to divert excess water to Mission Creek, modelling in 2020 showed that the 200-year peak flood had increased from 12 m3/s to 24.3 m3/s due to climate change, indicating that the structure was no longer suitable.

The City of Kelowna entrusted MidSea Engineering (part of CIMA+ since 2023) with upgrading the design of the diversion structure to increase its capacity and reduce the risk of flooding. The project was divided into two construction phases, the first achieving completion in mid-2023, and the second one in 2024. The City invested over $15 million, as part of a broader $55 million Mill Creek Flood Protection program, which is one of the largest and most complicated capital projects in Kelowna to date.

The objective of the project was to increase public and staff safety, enhance the hydraulics of the diversion structure to divert more water toward Mission Creek, improve debris management, and improve the upstream pass for spawning salmon that was blocked by the original structure.

Environmental consultation and contribution to sustainable development

Before this project began, the Okanagan Nation Alliance was consulted and all their requirements for environmental improvements were implemented. The project also required several permits, such as a water licence and authorizations under the Dike Maintenance Act, Dam Safety Regulation, and Fisheries Act.

To minimize the environmental impact, the project’s design was revised multiple times, resulting in reducing the number of trees that needed to be cut by more than half (only 70 trees instead of 150). Tree compensation was strategically planned as three new trees were planted for each tree felled during construction. The compensation plan was reviewed and approved by Fisheries and Oceans Canada – Pacific Region and the BC Ministry of Forests. To ensure that the project had no negative impact on fish habitats, strict regulations were implemented as per the Water Protection Act and the Water Sustainability Act. Our engineers undertook the design of many wildlife habitats, including fish pools, floodplains, creek riffles, engineered log jams and bird nests.

During the project, the project team faced the challenge of keeping the Okanagan Rail Trail—one of the most active bike and pedestrian paths in the city—open to the public. A parallel detour of approximately 500 metres was constructed to divert traffic, ensuring that the trail remained open during construction.

An award-winning project

CIMA+ earned the top prize in the Small to Medium Project category for the Mill Creek Flood Protection project at the 2025 Global Infrastructure Awards from FIDIC, the International Federation of Consulting Engineers. This prestigious recognition celebrates the project’s innovative and sustainable approach to climate-resilient infrastructure and places the City of Kelowna’s efforts on a global stage. The same year, CIMA+ received an Award of Excellence at the Canadian Consulting Engineering Awards for the project, one of the highest marks of recognition in the consulting engineering industry in Canada.